PHILIPPGRUPPE Aschaffenburg

🌉 Custom lifting solution for the Franklin Bridge in Mannheim. 🏗️

The Franklin Bridge in Mannheim is considered the longest integral wooden bridge in the world. For this extraordinary construction project, the 32 carbon-concrete slabs that make up the bridge deck were equipped with a custom-developed transport anchoring solution from the PHILIPPGRUPPE. 💪

The particular challenge: The precast carbon-concrete elements have a thin slab thickness and a conical geometry. A customized solution was therefore needed to ensure safe transport and precise installation. ⚙️

Four short, shallow-embedded stainless steel flat steel anchors were used. In combination with a leveling sling, the concrete slabs were safely transported, precisely positioned, and successfully installed. 🤝

The result: A custom transport anchor solution for a challenging bridge project—safe, reliable, and successfully implemented in practice. 🚀

👉 Click here to view the Franklin-Steg reference project in Mannheim

👉 Click here to see more reference projects

👉 Click here to view our transport anchors

NEWS CATEGORIES
KEYWORDS
Scroll to Top

The PHILIPPGRUPPEis your competent partner for high-quality products in the fields of construction technology, rope and lifting technology and hydraulics.

Address: Lilienthalstraße 7-9, 63741 Aschaffenburg
Phone: +49 6021 40 27-0
Business hours: ·
Aussenaufnahme einer Baustelle mit einer in Betonfertigteil integrierten Verbindungsschiene zur Montage von Bauteilen
Nahaufnahme von Verbindung eines Drahtseils mit verpresster Schlaufe und Drehgelenk
Detailaufnahme von Hydraulik-Anschlüssen und Schlauchverbindungen
Groß dimensioniertes Carbon-Betonfertigteil hängend an verschiedenen Anschlagketten
Prüfung von Lasthaken mit einem Magnetpulver-Prüfgerät
Dreh-Kippgestell der PHILIPPGRUPPE an einem Lasthaken in einer Fabrikhalle